PREPARATION:
Demolition agent;
Clean and cold water;
Plastic or metal bucket;
Beater or wooden rod for mixing;
Safety goggles;
Rubber gloves;
Dust-proof mask(required)
Helmet(required)
Thermometer(required)
Cap(wooden or iron wedge)
|
 |
 |
Mixing
- For regular safety reasons and mixing small amounts by hand, it is recommended to use rubber gloves.
- In a bucket, combine 1.5 Liters of water to one 5kgs bag of CRACKAG. Or pour water and CRACKAG as a rate of 1:3 units by weight.
- Mix well, using a drill and paddle is recommended. If mixing with a stick or other method, make sure powder is completely dissolved into the water. Mix to a slurry.
Filling
- Clean holes before filling using air hose remove excess dust from drilling.
- CRACKAG slurry should be poured into holes within 10-15 min. after mixing. Do not fill to the top, only fill the holes about 15mm ( ½” to 1”) from the top.
- Mix well and pour into holes while agitating the hole to make sure no air gaps are in the hole. Example: Using a piece of rod or stick to poke holes.
- For Horizontal holes, a grouting pump would be most reliable to poor.
|
|
|
|